Nr |
WP |
Title |
Date |
Nature |
Dissemination
Level |
|
|
| D01 |
WP 1 |
Project Execution Plan
|
2007-01-01 |
Re |
RE |
|
|
| D02 |
WP 2 |
State of the art on THMC
|
2007-10-01 |
Re |
PU |
|
|
| D03 |
WP 2 |
Summary of the end-user needs for the project (1 month after end users group workshop)
|
2007-06-01 |
Re |
PU |
|
|
| D04 |
WP 6 |
Short report on the current handling of the damaged zone in integrated PA
|
2007-10-01 |
Re |
RE |
|
|
| D05 |
WP 3.1 |
THM characterisation and input for constitutive law
|
2009-04-01 |
Re |
RE |
|
|
| D06 |
WP 3.2 |
Thermally induced modifications of clays
|
2009-04-01 |
Re |
RE |
|
|
| D07 |
WP 3.3 |
Simulation laboratory tests
|
2009-10-01 |
Re |
RE |
|
|
| D08 |
WP 4.1 |
Small scale in-situ tests
|
2009-10-01 |
Re |
RE |
|
|
| D09 |
WP 4.3 |
Thermal impact on the stability of the lining
|
2009-10-01 |
Re |
RE |
|
|
| D10 |
WP 5.1 |
Constitutive models development
|
2009-10-01 |
Re |
RE |
|
|
| D11 |
WP 4.2 |
PRACLAY experimental results
|
2010-10-01 |
Re |
RE |
|
|
| D12 |
WP 4.2 |
Processing and interpretation of ultrasonic data from the PRACLAY experiment
|
2010-10-01 |
Re |
RE |
|
|
| D13 |
WP 5.2 |
Benchmark exercises and conclusions on relevant issues for a safety case
|
2010-10-01 |
Re |
PU |
|
|
| D14 |
WP 6 |
Report on the integration of TIMODAZ results within the safety case and recommendations for repository design.
|
2010-10-01 |
Re |
PU |
|
|
| D15 |
WP 1 |
Technical and management reports (including the final report)
|
2010-10-01 |
Re |
PU |